Date Ryan and Dallin Ben and Daniel
Jan 23 - Jan 27 Power Supply Chassis
Jan 30 - Feb 03 Construct new Scanner Shield Debug current Scanner Shield
Feb 06 - Feb 10 Construct new Scanner Shield Debug current Scanner Shield
Feb 13 - Feb 17 Polygon and Galvos RF Boards
Feb 20 - Feb 24 Test RF Boards Test Scanning System
Feb 27 - Mar 03 Align optics Assemble Monitor
Mar 06 - Mar 10 More RF Chains Hardware adjustments
Mar 13 - Apr 07 Software Adjustments Software Adjustments

Consequences: If you do not finish your project - you are in charge bringing treats to the next meeting

Checklist

ItemStatus
Cut 6 1/4“ pegs (band saw)Done
Put connectors on all power wiresDone
Label wiresDone
Split power for fanDone
Mirror pieces aligned for optics
3D print mirror piecesDone
Block laser blob (tape?)
Support RF chain
Connect all power
Laser print panelDone
Connect fanDone

Band Pass Filter (1 Hour)


Testing the scanning system (3.5 Hour)



Mixer (1 Hour)


Hela-10 (2 hours)


Polygon and Galvanometer (4 hours)


Power Supply (3 hours)